==CGI Build Process & Testing ==
* Currently we are on a 3 week CGI software release schedule. See [[CGI_Build_Schedule]] for more details.
* The buildmeister follows this [[CGI_Build_Process | process]].
* When the CGIs are loaded on hgwbeta, the QA'er tests their [[CGI_testing_responsibilities | assigned CGIs]]. The general CGI testing instructions can be found [[CGI_Testing |here]].
==Mailing List==
==Mailing List==
* Mailing list schedule can be found on the [https://kkstore.cse.ucsc.edu/calendar/plans.cgi?active_tab=0 QA group calendar] (Note: where it says '''Calendar:''', you will need to change the drop down from "Main" to "QA" to view.)
* Mailing list schedule can be found on the [https://kkstore.cse.ucsc.edu/calendar/plans.cgi?active_tab=0 QA group calendar] (Note: where it says '''Calendar:''', you will need to change the drop down from "Main" to "QA" to view.)

Revision as of 20:55, 24 March 2011

CGI Build Process & Testing

  • Currently we are on a 3 week CGI software release schedule. See CGI_Build_Schedule for more details.
  • The buildmeister follows this process.
  • When the CGIs are loaded on hgwbeta, the QA'er tests their assigned CGIs. The general CGI testing instructions can be found here.

Mailing List